The Federal Government plans to add 984 megawatts of electricity transmission capacity through upgrades to five substations under the Presidential Power Initiative (PPI), as it seeks to ease grid bottlenecks and improve power delivery across the country.
The projects will cover New Abeokuta, Onitsha, Ayede, Sokoto and Offa substations, with the New Abeokuta upgrade expected to contribute 480MW. Power Minister Joseph Tegbe disclosed this during a technical inspection of the project in Ogun State, which involves upgrading the existing 132/33kV facility to a modern 330/132/33kV substation.
The New Abeokuta project, being undertaken by Siemens Energy, will feature two 300MVA transformers, alongside four 330kV and four 132kV transmission line bays. The upgrade is expected to improve electricity transmission reliability and support industrial, commercial and residential demand across Ogun State.
The other interventions will include replacing Onitsha’s 90MVA transformer with a 300MVA unit to add 240MW, replacing a burnt 150MVA transformer at Ayede to provide 120MW, installing two 60MVA transformers at Sokoto for 96MW and adding four 132kV line bays and a 60MVA transformer at Offa to deliver 48MW. The five projects are expected to provide a combined 984MW of additional transmission capacity.
FGN Power Company said it was also working to complete 16 Phase One transmission line projects spanning 606.5 kilometres, including the 38km Ajah–Shapaati line. Managing Director Kenny Anuwe said the initiative was designed to address infrastructure gaps across the electricity value chain, noting that the pilot phase had already delivered 1,080MW of additional wheeling capacity through 10 power transformers and 10 mobile substations. More information on the initiative is available through FGN Power Company.